Improving the Energy Efficiency in a Commercial Building
Energy Consumption project - 6000 sq ft commercial facility case study
Customer: 6000 SQ FT COMMERCIAL FACILITY
Location: Marshalls Creek, Pennsylvania
Date: March/April 2016
The tests conducted at the Basic Power, Inc. production facility in East Stroudsburg, PA demonstrate that the BPU™ technology reduces kW consumption and that this reduction can be observed using the Acuvim II meter in combination with the Acuview software.
These tests also show that there is a nominal reduction of kW at the utility mains when a load is connected to an additional transformer on the facility side of the utility meter and that placing an appropriately sized BPU™ unit at the panel connected to the transformer will reduce kW on that part of the service.